Time Value of Money: Present Value, Future Value and Annuity Formulas

By 3FOLD Training's CCP curriculum team · reviewed against the CCP Candidate Handbook · Updated 24 November 2026 · 7 min read

Quick answer: The time value of money says a dollar today is worth more than a dollar later, because it can earn a return. Future value is FV = PV × (1 + i)^n, and present value is PV = FV / (1 + i)^n. For a level annual payment A, the present value is A × [1 − (1 + i)^−n] / i. These three formulas underlie NPV, IRR, payback and life cycle costing.
Free Course Info

Get CCP® Training Details

Syllabus · LMS · Pricing — no spam.

Phone *

Your details are kept private and never shared.

Why money has a time value

If you can invest money at 7% a year, 10,000 today becomes more than 10,000 next year. So when a project spends or earns money at different times, you can't just add the amounts up. You have to move them to a common point in time first. That's all the time value of money does, and it's the foundation of NPV and IRR.

Future value

FV = PV × (1 + i)^n, where i is the interest rate per period and n the number of periods. Example: 10,000 invested at 7% for 5 years grows to 10,000 × 1.07⁵ = 14,026.

Present value

Present value runs the same formula backwards: PV = FV / (1 + i)^n. Example: you will receive 20,000 in 4 years and your discount rate is 8%. PV = 20,000 / 1.08⁴ = 14,701. Receiving 20,000 in four years is worth about 14,700 today at that rate.

Annuities: level repeated payments

Many cost problems involve the same amount every year, such as maintenance or energy cost. The present value of a level annual amount A for n years is PV = A × [1 − (1 + i)^−n] / i.

  • Present value example: 1,000 a year for 10 years at 8% has a present value of 1,000 × 6.7101 = 6,710.
  • Future value example: the same payments accumulate to 1,000 × [(1.08¹⁰ − 1) / 0.08] = 14,487 at year 10.

A quick check: the rule of 72

To estimate how long money takes to double, divide 72 by the interest rate in percent. At 6%, 72 / 6 = 12 years. The exact figure is about 11.9 years, so the rule is a useful sanity check, not a substitute for the formula.

Common mistakes

  • Mixing periods: using an annual rate with monthly cash flows, or the reverse.
  • Mixing real and nominal values. If cash flows include inflation, use a nominal discount rate; if not, use a real one.
  • Forgetting timing. Annuity formulas assume payments at the end of each period.
  • Using the wrong rate. The discount rate should reflect the organisation's required return, not just the loan rate.

Where it's used in cost engineering

Time value of money drives life cycle costing, benefit-cost analysis, lease-or-buy decisions and depreciation comparisons. It is also part of the CCP® exam's calculation topics (see our formula guide), and CCP Complete Self-Paced Preparation covers it with the other exam domains.

Frequently asked questions

What is the time value of money?+
The time value of money is the principle that a sum received today is worth more than the same sum received later, because money available now can be invested to earn a return.
What is the formula for future value?+
The future value formula is FV = PV × (1 + i)^n, where PV is the present amount, i is the interest rate per period and n is the number of periods.
What is the formula for present value?+
The present value formula is PV = FV / (1 + i)^n, which discounts a future amount back to today at interest rate i over n periods.
What is an annuity in engineering economics?+
An annuity in engineering economics is a series of equal payments at regular intervals, such as annual maintenance cost, and its present value is A × [1 − (1 + i)^−n] / i.

Prepare with an AACE-Approved Provider