Why money has a time value
If you can invest money at 7% a year, 10,000 today becomes more than 10,000 next year. So when a project spends or earns money at different times, you can't just add the amounts up. You have to move them to a common point in time first. That's all the time value of money does, and it's the foundation of NPV and IRR.
Future value
FV = PV × (1 + i)^n, where i is the interest rate per period and n the number of periods. Example: 10,000 invested at 7% for 5 years grows to 10,000 × 1.07⁵ = 14,026.
Present value
Present value runs the same formula backwards: PV = FV / (1 + i)^n. Example: you will receive 20,000 in 4 years and your discount rate is 8%. PV = 20,000 / 1.08⁴ = 14,701. Receiving 20,000 in four years is worth about 14,700 today at that rate.
Annuities: level repeated payments
Many cost problems involve the same amount every year, such as maintenance or energy cost. The present value of a level annual amount A for n years is PV = A × [1 − (1 + i)^−n] / i.
- Present value example: 1,000 a year for 10 years at 8% has a present value of 1,000 × 6.7101 = 6,710.
- Future value example: the same payments accumulate to 1,000 × [(1.08¹⁰ − 1) / 0.08] = 14,487 at year 10.
A quick check: the rule of 72
To estimate how long money takes to double, divide 72 by the interest rate in percent. At 6%, 72 / 6 = 12 years. The exact figure is about 11.9 years, so the rule is a useful sanity check, not a substitute for the formula.
Common mistakes
- Mixing periods: using an annual rate with monthly cash flows, or the reverse.
- Mixing real and nominal values. If cash flows include inflation, use a nominal discount rate; if not, use a real one.
- Forgetting timing. Annuity formulas assume payments at the end of each period.
- Using the wrong rate. The discount rate should reflect the organisation's required return, not just the loan rate.
Where it's used in cost engineering
Time value of money drives life cycle costing, benefit-cost analysis, lease-or-buy decisions and depreciation comparisons. It is also part of the CCP® exam's calculation topics (see our formula guide), and CCP Complete Self-Paced Preparation covers it with the other exam domains.
Frequently asked questions
What is the time value of money?+
What is the formula for future value?+
What is the formula for present value?+
What is an annuity in engineering economics?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →