Life Cycle Costing (LCC): How to Compare Options Beyond the Capital Cost

By 3FOLD Training's CCP curriculum team · reviewed against the CCP Candidate Handbook · Updated 23 November 2026 · 7 min read

Quick answer: Life cycle costing (LCC) compares options by the total cost of owning an asset over its life, not only its purchase or construction cost. It includes acquisition, operation, maintenance, replacement and disposal costs, usually discounted to present value. ISO 15686-5:2017 sets requirements and guidance for LCC of buildings and constructed assets.
Free Course Info

Get CCP® Training Details

Syllabus · LMS · Pricing — no spam.

Phone *

Your details are kept private and never shared.

The idea

The cheapest asset to build is often not the cheapest to own. A cheaper air-conditioning plant may cost more to run and replace; a cheaper cladding may need earlier repair. Life cycle costing puts all those future costs next to the capital cost so you can compare options fairly.

What ISO 15686-5 covers

ISO 15686-5:2017, Buildings and constructed assets: Service life planning, Part 5: Life-cycle costing, gives requirements and guidance for LCC analysis of buildings and constructed assets, new or existing. It describes LCC as covering costs and cash flows from acquisition through operation to disposal, and typically compares alternatives over an agreed period of analysis. The standard also distinguishes LCC from whole-life cost, which is broader: it adds non-construction costs, externalities and income.

Typical cost categories

PhaseExamples
Construction / acquisitionDesign, fees, construction, initial fit-out
OperationEnergy, utilities, insurance, regulatory costs
MaintenancePlanned and reactive maintenance, repairs, cleaning, replacement of major components
End of lifeDecommissioning, disposal or demolition, residual value

A worked example

You are choosing between two chiller plants over a 20-year analysis period at a 6% discount rate. All figures are in dollars, and I've simplified by ignoring inflation, replacement and residual value.

Option A: standardOption B: high-efficiency
Capital cost1,000,0001,150,000
Annual running and maintenance cost40,00020,000
Present value of 20 years of annual cost458,797229,398
Life cycle cost (present value)1,458,7971,379,398

The present value factor for 20 years at 6% is (1 − 1.06⁻²⁰) / 0.06 = 11.4699, so A's annual cost is worth 40,000 × 11.4699 = 458,797 today. Option B costs 150,000 more up front, but its life cycle cost is about 79,400 lower. Choosing on capital cost alone would pick the wrong option.

Test the answer

The result depends on the discount rate, analysis period and the cost assumptions. At a much higher rate or a shorter period, the extra capital cost of B would be harder to recover. A good LCC study tests those sensitivities and shows the break-even point, rather than presenting one number as certain. Techniques such as Monte Carlo simulation can help when the inputs are very uncertain.

LCC uses the same discounting maths as NPV analysis. If that arithmetic is new, start with our NPV, IRR and payback guide.

Common mistakes

  • Leaving out replacement cycles for components that wear out before the end of the study period.
  • Using optimistic maintenance figures with no source.
  • Mixing real and nominal values. Choose one and be consistent with the discount rate.
  • Presenting LCC as precise. It's a comparison tool and results depend on assumptions.

LCC and the CCP

Engineering economics and time value of money are part of the CCP® exam. Practice with our formula guide, and see CCP Complete Self-Paced Preparation for full exam coverage. For the wider field, read what cost engineering is.

Frequently asked questions

What is life cycle costing (LCC)?+
Life cycle costing (LCC) compares options by the total cost of owning an asset over its life, including acquisition, operation, maintenance, replacement and disposal costs, usually discounted to present value.
What is the difference between life cycle cost and whole-life cost?+
Under ISO 15686-5, whole-life cost is broader than life cycle cost: it also includes non-construction costs, externalities and income, while life cycle cost covers the asset's own cost from acquisition through operation to disposal.
Which standard covers life cycle costing for buildings?+
ISO 15686-5:2017, Buildings and constructed assets, Service life planning, Part 5: Life-cycle costing, gives requirements and guidance for life cycle costing of buildings and constructed assets.
Why are future costs discounted in life cycle costing?+
Future costs are discounted in life cycle costing because money spent later is worth less in present terms, so discounting to present value lets costs that occur at different times be compared on one basis.

Prepare with an AACE-Approved Provider

2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.

Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →

WhatsAppEnrol — $590