Get CCP® Training Details
Syllabus · LMS · Pricing — no spam.
What the ratio measures
Benefit-cost analysis compares everything a project delivers with everything it costs, with both discounted to present value using the time value of money. BCR = PV of benefits / PV of costs. It's a ratio, so it tells you how much value you get per unit of cost.
A worked example
A water-saving scheme costs 1,500,000 to build. It saves 300,000 a year for 10 years. The discount rate is 8%.
- Present value of benefits = 300,000 × [1 − 1.08⁻¹⁰] / 0.08 = 300,000 × 6.7101 = 2,013,024.
- Present value of costs = 1,500,000 (all spent up front).
- BCR = 2,013,024 / 1,500,000 = 1.34.
- NPV = 2,013,024 − 1,500,000 = 513,024.
BCR is above 1.0 and NPV is positive. The two always agree on whether a single project is worthwhile: BCR > 1 exactly when NPV > 0.
The decision rule
- One project: accept if BCR is greater than 1.0.
- Choosing between mutually exclusive options: don't pick the highest BCR. Calculate the incremental BCR of the larger option over the smaller; if it is above 1.0, the extra spending is justified. Or compare NPVs directly.
- Budget-limited portfolios: ranking by BCR is a useful guide for choosing among independent projects when money is limited.
Pitfalls
- Where you put a cost matters. Counting operating savings as a reduction in cost versus as a benefit changes the ratio but not the NPV, so be consistent.
- Soft benefits. Time saved or safety improvements need defensible values. Show the assumptions.
- Optimistic benefits and pessimistic costs. Test the ratio against a cost overrun and a benefit shortfall. If BCR falls below 1.0 with a modest change, the case is fragile.
- Discount rate. A small change in rate can move a long-life project a lot. Run sensitivities.
How it connects to the other tools
BCR, NPV and IRR use the same discounted cash flows, and life cycle costing covers cases where only costs differ. For a first screen of an investment on volume rather than value, see break-even analysis. Preparing for the CCP®? Our CCP Complete Self-Paced Preparation includes the engineering economics topics.
Frequently asked questions
What is the benefit-cost ratio?+
How is BCR related to NPV?+
Should I choose the option with the highest BCR?+
What is a good benefit-cost ratio?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →
