What depreciation does
An asset such as a crane or a pump loses value as it's used. Depreciation is the accounting allocation of its cost over its useful life, so each year's cost reflects the use of the asset. It's a non-cash charge, but it affects taxable income, which is why it appears in engineering economics studies alongside time value of money.
Terms
- Cost basis: the installed cost of the asset.
- Salvage value: the estimated value at the end of its life.
- Useful life (n): the number of years over which it's depreciated.
- Book value: cost less accumulated depreciation.
One asset, three methods
An asset costs 100,000, has a salvage value of 10,000 and a 5-year life.
1. Straight-line
Annual depreciation = (100,000 − 10,000) / 5 = 18,000 in every year.
2. Double-declining balance
Each year's charge is the opening book value × 2 / n, where n is the life, so 40% here. The method ignores salvage value in the calculation, but book value is not depreciated below salvage.
3. Sum-of-years' digits
The sum of the digits for 5 years is 1 + 2 + 3 + 4 + 5 = 15. Year 1 charge = 5/15 of the depreciable amount (90,000), year 2 = 4/15, and so on.
| Year | Straight-line | Double-declining balance | Sum-of-years' digits |
|---|---|---|---|
| 1 | 18,000 | 40,000 | 30,000 |
| 2 | 18,000 | 24,000 | 24,000 |
| 3 | 18,000 | 14,400 | 18,000 |
| 4 | 18,000 | 8,640 | 12,000 |
| 5 | 18,000 | 2,960 | 6,000 |
| Total | 90,000 | 90,000 | 90,000 |
In year 5 the declining-balance method charges only 2,960 rather than 40% of 12,960 = 5,184, because the book value can't go below the 10,000 salvage value. All three methods write off the same total of 90,000; they differ in how early.
Which method is used?
The method used in practice is usually set by accounting standards and tax rules, which differ by country, so in a project study you normally follow the rules the owner applies. Straight-line is the simplest and the default in many internal studies. Accelerated methods give larger early deductions, which can improve after-tax cash flow in the early years.
Depreciation and the CCP
Straight-line depreciation is one of the formulas listed among the CCP® exam's engineering economics topics. See our formula guide and the wider study resources in CCP Complete Self-Paced Preparation.
Frequently asked questions
What is depreciation in engineering economics?+
What is the straight-line depreciation formula?+
What is the difference between straight-line and declining balance depreciation?+
Do all depreciation methods give the same total?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →