How activities are linked
A schedule is a network of activities, and the logic between them determines the critical path. In the precedence diagramming method (PDM), each activity is a node and each link states how the successor depends on the predecessor.
The four relationships
| Type | Meaning | Example |
|---|---|---|
| Finish-to-start (FS) | Successor can't start until the predecessor finishes | Pour slab (predecessor), then erect formwork for the next level |
| Start-to-start (SS) | Successor can't start until the predecessor has started | Start laying cable tray once pipework begins on the same floor |
| Finish-to-finish (FF) | Successor can't finish until the predecessor finishes | Testing can't finish until commissioning finishes |
| Start-to-finish (SF) | Successor can't finish until the predecessor starts | Old system can't be switched off until the new one starts (rare) |
FS is the default and the easiest to read. SS and FF let activities overlap, which shortens the schedule but makes it harder to follow and to analyse for float.
Lead and lag
- Lag adds time between linked activities: a +3 day lag on an FS link between 'pour concrete' and 'strip formwork' represents curing time.
- Lead lets the successor start before the predecessor finishes: a lead of 2 days on 'pour slab' to 'erect formwork' means the next activity starts 2 days before the slab is complete. A lead is a negative lag.
Example: paint (5 days) follows plastering (6 days). With FS and no lag, the paint starts on day 6. With an SS link and a lag of 3 days instead, painting starts on day 3 of plastering and, if painting is shorter than plastering, a separate FF link may be needed to stop it finishing before the plastering does.
Common mistakes
- Lag used as hidden float. If a lag really stands for an activity (curing, approval, delivery), model it as an activity so it's visible and can carry its own resources and dates.
- Too many SS and FF links. The schedule becomes hard to review and float figures become hard to interpret.
- Open ends. Activities with no predecessor or no successor often hide missing logic.
- Leads that make the schedule unrealistic. Check that the physical work can overlap in the way the lead assumes.
A quick test of the logic
Change one activity's duration and see whether the finish date moves the way you expect. If it doesn't, check the links. Good scheduling logic is what makes cost-loaded schedules and S-curves reliable. See the work breakdown structure for how activities are derived from scope.
Scheduling and the CCP
Scheduling is a CCP® exam domain, and the exam expects you to understand logic, float and the critical path conceptually, not to operate a particular software tool. CCP Complete Self-Paced Preparation covers it with the other domains.
Frequently asked questions
What are the four types of schedule dependencies?+
What is the difference between lead and lag in scheduling?+
What is a finish-to-start dependency?+
Why is start-to-finish rarely used?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →