Schedule Dependencies Explained: FS, SS, FF, SF, Lead and Lag

By 3FOLD Training's CCP curriculum team · reviewed against the CCP Candidate Handbook · Updated 24 November 2026 · 6 min read

Quick answer: In the precedence diagramming method, activities are linked by four relationships: finish-to-start (FS, the successor starts when the predecessor finishes), start-to-start (SS), finish-to-finish (FF) and start-to-finish (SF, rare). A lead lets a successor start earlier than the link would allow, and a lag adds a delay. Finish-to-start is by far the most common and the safest default.
Free Course Info

Get CCP® Training Details

Syllabus · LMS · Pricing — no spam.

Phone *

Your details are kept private and never shared.

How activities are linked

A schedule is a network of activities, and the logic between them determines the critical path. In the precedence diagramming method (PDM), each activity is a node and each link states how the successor depends on the predecessor.

The four relationships

TypeMeaningExample
Finish-to-start (FS)Successor can't start until the predecessor finishesPour slab (predecessor), then erect formwork for the next level
Start-to-start (SS)Successor can't start until the predecessor has startedStart laying cable tray once pipework begins on the same floor
Finish-to-finish (FF)Successor can't finish until the predecessor finishesTesting can't finish until commissioning finishes
Start-to-finish (SF)Successor can't finish until the predecessor startsOld system can't be switched off until the new one starts (rare)

FS is the default and the easiest to read. SS and FF let activities overlap, which shortens the schedule but makes it harder to follow and to analyse for float.

Lead and lag

  • Lag adds time between linked activities: a +3 day lag on an FS link between 'pour concrete' and 'strip formwork' represents curing time.
  • Lead lets the successor start before the predecessor finishes: a lead of 2 days on 'pour slab' to 'erect formwork' means the next activity starts 2 days before the slab is complete. A lead is a negative lag.

Example: paint (5 days) follows plastering (6 days). With FS and no lag, the paint starts on day 6. With an SS link and a lag of 3 days instead, painting starts on day 3 of plastering and, if painting is shorter than plastering, a separate FF link may be needed to stop it finishing before the plastering does.

Common mistakes

  • Lag used as hidden float. If a lag really stands for an activity (curing, approval, delivery), model it as an activity so it's visible and can carry its own resources and dates.
  • Too many SS and FF links. The schedule becomes hard to review and float figures become hard to interpret.
  • Open ends. Activities with no predecessor or no successor often hide missing logic.
  • Leads that make the schedule unrealistic. Check that the physical work can overlap in the way the lead assumes.

A quick test of the logic

Change one activity's duration and see whether the finish date moves the way you expect. If it doesn't, check the links. Good scheduling logic is what makes cost-loaded schedules and S-curves reliable. See the work breakdown structure for how activities are derived from scope.

Scheduling and the CCP

Scheduling is a CCP® exam domain, and the exam expects you to understand logic, float and the critical path conceptually, not to operate a particular software tool. CCP Complete Self-Paced Preparation covers it with the other domains.

Frequently asked questions

What are the four types of schedule dependencies?+
The four types of schedule dependencies in the precedence diagramming method are finish-to-start (FS), start-to-start (SS), finish-to-finish (FF) and start-to-finish (SF), with finish-to-start being the most common.
What is the difference between lead and lag in scheduling?+
In project scheduling, a lag adds a delay between linked activities, such as curing time, while a lead lets the successor activity start before the predecessor finishes; a lead is a negative lag.
What is a finish-to-start dependency?+
A finish-to-start (FS) dependency is a schedule relationship in which the successor activity cannot start until the predecessor activity has finished, and it is the default relationship in most schedules.
Why is start-to-finish rarely used?+
A start-to-finish (SF) dependency, where the successor cannot finish until the predecessor starts, is rarely used in project schedules because few real situations need it and it is hard to read.

Prepare with an AACE-Approved Provider

2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.

Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →

WhatsAppEnrol — $590