The S-Curve in Project Management: How to Build It and What It Tells You

By 3FOLD Training's CCP curriculum team · reviewed against the CCP Candidate Handbook · Updated 23 November 2026 · 6 min read

Quick answer: An S-curve is a graph of cumulative cost, hours or progress plotted against time. It's usually shaped like an S because work starts slowly, speeds up in the middle and slows down near the end. Plotting the planned curve (PV) against earned value (EV) and actual cost (AC) shows at a glance whether a project is ahead or behind, and over or under budget.
Free Course Info

Get CCP® Training Details

Syllabus · LMS · Pricing — no spam.

Phone *

Your details are kept private and never shared.

Why the curve is S-shaped

At the start of a project, spending is slow: design, approvals and mobilisation. In the middle, construction or fabrication is in full swing and the curve climbs steeply. Towards the end, work tails off into commissioning, punch lists and close-out, and the curve flattens. Plot the running total and you get the familiar S.

How to build one

  1. Start from a cost-loaded or resource-loaded schedule, so each activity has a budget and dates.
  2. Spread each activity's budget across the periods it runs in (weekly or monthly).
  3. Add up the budget for every period.
  4. Plot the cumulative total against time. That's your planned value (PV) curve, or baseline.

If the schedule isn't cost-loaded, a rough curve can be built from manhours or from a standard distribution, but it will be less reliable. AACE's CCP blueprint includes supporting cost and resource loading summaries based on project schedules, which is exactly this exercise.

Reading the three curves together

Once the project is running, add two more lines: earned value (EV), the budgeted cost of the work actually done, and actual cost (AC), what that work cost.

What you seeWhat it means
EV below PVBehind schedule (less work done than planned)
EV above PVAhead of schedule
AC above EVOver budget for the work done
AC below EVUnder budget for the work done

The gaps between the curves are the variances in earned value management: schedule variance is EV − PV and cost variance is EV − AC.

Common mistakes

The most frequent one is comparing actual cost straight against the planned curve. A project can spend exactly to plan while delivering far less work, and the S-curve will look healthy until someone adds the earned value line. Another is forgetting to re-baseline after approved changes, so the planned curve no longer reflects the agreed scope.

Other uses

S-curves are also used for cash-flow forecasting, which helps owners plan funding; for manpower planning; and for progress reporting to clients. In AACE's CCP blueprint, cash-flow analysis appears under Domain 3, Create Reports and Documentation, and forecasting funding requirements under Domain 1. For the related calculations, see our formulas guide.

Frequently asked questions

What is an S-curve?+
An S-curve in project management is a graph of cumulative cost, hours or progress against time, typically S-shaped.
Why is it shaped like an S?+
A project S-curve is shaped like an S because work starts slowly, accelerates in the middle and slows towards completion.
What does it mean if actual cost is above the planned curve?+
If actual cost is above the planned S-curve it does not necessarily mean an overrun; compare actual cost with earned value to see whether you're over budget for the work done.
How do I create an S-curve?+
To create an S-curve, spread each activity's budget over its schedule dates, total by period and plot the cumulative figure.

Prepare with an AACE-Approved Provider

2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.

Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →

WhatsAppEnrol — $590