Why the curve is S-shaped
At the start of a project, spending is slow: design, approvals and mobilisation. In the middle, construction or fabrication is in full swing and the curve climbs steeply. Towards the end, work tails off into commissioning, punch lists and close-out, and the curve flattens. Plot the running total and you get the familiar S.
How to build one
- Start from a cost-loaded or resource-loaded schedule, so each activity has a budget and dates.
- Spread each activity's budget across the periods it runs in (weekly or monthly).
- Add up the budget for every period.
- Plot the cumulative total against time. That's your planned value (PV) curve, or baseline.
If the schedule isn't cost-loaded, a rough curve can be built from manhours or from a standard distribution, but it will be less reliable. AACE's CCP blueprint includes supporting cost and resource loading summaries based on project schedules, which is exactly this exercise.
Reading the three curves together
Once the project is running, add two more lines: earned value (EV), the budgeted cost of the work actually done, and actual cost (AC), what that work cost.
| What you see | What it means |
|---|---|
| EV below PV | Behind schedule (less work done than planned) |
| EV above PV | Ahead of schedule |
| AC above EV | Over budget for the work done |
| AC below EV | Under budget for the work done |
The gaps between the curves are the variances in earned value management: schedule variance is EV − PV and cost variance is EV − AC.
Common mistakes
The most frequent one is comparing actual cost straight against the planned curve. A project can spend exactly to plan while delivering far less work, and the S-curve will look healthy until someone adds the earned value line. Another is forgetting to re-baseline after approved changes, so the planned curve no longer reflects the agreed scope.
Other uses
S-curves are also used for cash-flow forecasting, which helps owners plan funding; for manpower planning; and for progress reporting to clients. In AACE's CCP blueprint, cash-flow analysis appears under Domain 3, Create Reports and Documentation, and forecasting funding requirements under Domain 1. For the related calculations, see our formulas guide.
Frequently asked questions
What is an S-curve?+
Why is it shaped like an S?+
What does it mean if actual cost is above the planned curve?+
How do I create an S-curve?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →