Total Float vs Free Float: What the Difference Means on a Schedule

By 3FOLD Training's CCP curriculum team · reviewed against the CCP Candidate Handbook · Updated 24 November 2026 · 7 min read

Quick answer: Total float is how long an activity can be delayed without delaying the project finish date (late start − early start). Free float is how long it can be delayed without delaying the early start of any successor activity. Free float can never exceed total float, and an activity can have total float but zero free float, in which case delaying it uses up its successors' float.
Free Course Info

Get CCP® Training Details

Syllabus · LMS · Pricing — no spam.

Phone *

Your details are kept private and never shared.

The two definitions

  • Total float = late start − early start (or late finish − early finish). It's the delay the project can absorb on that path before the finish date moves.
  • Free float = the earliest early start among the successors − the activity's early finish (with finish-to-start logic). It's the delay that changes nothing for anyone else.

Activities on the critical path have zero total float. Float is a property of the schedule logic, not of the activity itself, so it changes whenever logic or durations change.

A worked example

Six activities, finish-to-start logic. A (3 days) is first. B (4) and C (2) follow A. D (5) follows B. E (3) follows C. F (2) follows both D and E.

Forward pass

  • A: 0–3. B: 3–7. C: 3–5. E: 5–8. D: 7–12.
  • F can start only when both D (12) and E (8) are done, so F: 12–14. The project takes 14 days.

Backward pass and float

ActivityEarly startLate startTotal floatFree float
A0000
B3300
D7700
F121200
C3740
E5944

The critical path is A–B–D–F. Activities C and E form a parallel path with 4 days of total float, shared between them. C has 4 days of total float but 0 days of free float: E starts the moment C finishes, so if C slips even one day, E's start slips with it. E has 4 days of free float, because nothing is waiting on it except F, which can't start until day 12 anyway.

The two activities share the same 4 days. If C uses 3 of them, E has only 1 left. That is the practical meaning of total float: it belongs to the path, not to the activity.

Why it matters on a project

  • Resource levelling. You can move activities with float to even out labour, but check free float first to avoid disturbing successors.
  • Priority. Activities with little float need attention first. Near-critical paths can become critical after a small slip.
  • Delay claims. Contracts differ on who owns float. Some treat it as belonging to the project, others to whoever uses it first. Check your contract (this is general information, not legal advice).

Common mistakes

  • Reading total float as private time for one activity when several activities share it.
  • Constraints (fixed dates) that create artificial float or remove real float.
  • Missing logic that makes an activity look like it has a lot of float.

Dependencies other than finish-to-start change how float is calculated; see schedule dependencies, lead and lag. Scheduling is a CCP® exam topic, covered in CCP Complete Self-Paced Preparation.

Frequently asked questions

What is total float in project scheduling?+
Total float in project scheduling is the amount of time an activity can be delayed without delaying the project finish date, calculated as late start minus early start.
What is free float in project scheduling?+
Free float is the amount of time an activity can be delayed without delaying the early start of any successor activity, so it never exceeds the activity's total float.
Can an activity have total float but no free float?+
Yes, an activity can have total float but zero free float when a successor starts immediately after it, so any delay uses up the successor's float even though the project end date is safe for now.
What is the float on the critical path?+
Activities on the critical path have zero total float, which means any delay to them delays the project finish date.

Prepare with an AACE-Approved Provider

2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.

Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →

WhatsAppEnrol — $590