Where CPM came from
CPM was developed jointly by DuPont and Remington Rand's Univac division. According to Kelley and Walker's own account published by PMI, the work ran from December 1956 to February 1959, and the method was presented publicly in 1959. They set out to see whether a computer could calculate project schedules from the logic of the work rather than from a bar chart. The core idea has not changed much since.
The idea in one paragraph
Every project is a network of activities linked by dependencies. Some chains of activities are longer than others. The longest chain from start to finish determines the earliest the project can finish, and that is the critical path. Activities not on it have some spare time, called float (or slack), in which they can slip without delaying the end date.
A worked example
Take four activities. A (3 days) must finish before B (4 days) and C (2 days) can start. D (5 days) can start only when both B and C are finished.
Forward pass: earliest dates
- A: starts day 0, finishes day 3.
- B: starts 3, finishes 7. C: starts 3, finishes 5.
- D: can't start until both B (day 7) and C (day 5) are done, so it starts at 7 and finishes at 12.
The project duration is 12 days.
Backward pass: latest dates
- D must finish by day 12, so it must start by day 7.
- B must finish by day 7, so it must start by day 3. C must also finish by day 7, so it can start as late as day 5.
- A must finish by day 3 (B and C both need it at day 3 at the latest), so it must start at day 0.
Float and the critical path
| Activity | Duration | Earliest start | Latest start | Total float |
|---|---|---|---|---|
| A | 3 | 0 | 0 | 0 |
| B | 4 | 3 | 3 | 0 |
| C | 2 | 3 | 5 | 2 |
| D | 5 | 7 | 7 | 0 |
Activities A, B and D have zero float, so the critical path is A–B–D, 12 days. C has 2 days of float: it can slip by two days without moving the end date. If B slips by one day, the whole project slips one day.
What this means on a real project
- Focus effort on the critical path. Time saved there shortens the project; time saved elsewhere often doesn't.
- Watch near-critical paths. A project can have several parallel near-critical paths, and a small slip can make one of them critical.
- The path moves. As progress is updated, the critical path can change, so it has to be recalculated every update.
- Float belongs to the project. Agree how float is used in the contract, because it affects delay claims.
Common scheduling mistakes
- Missing logic links, so activities appear to have lots of float when they don't.
- Too many constraints (fixed dates) that override the logic and hide the real critical path.
- Long-duration activities that should have been broken down.
- Never testing the schedule. Change one duration and check the end date moves as you'd expect.
Linking schedule and cost
Time and cost are managed together in cost engineering. A cost-loaded schedule gives you the planned spend curve (see S-curves) and is what earned value measures progress against. Scheduling is a CCP® exam domain in its own right, and our CCP Complete Self-Paced Preparation course covers it alongside cost topics.
Frequently asked questions
What is the critical path method (CPM)?+
Who developed the critical path method?+
What is float in the critical path method?+
Can a project have more than one critical path?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →