What a baseline is for
You can't say whether a project is on track without something agreed to compare it to. The baseline is that something. It's a frozen, approved snapshot of the plan, so that when reality moves, you can see by how much and why. If the plan keeps changing silently, nobody can tell whether performance is good or bad.
The three baselines
| Baseline | Contains | Typically comes from |
|---|---|---|
| Scope | Scope statement, WBS and the description of each element | Requirements and WBS |
| Schedule | Approved activities, logic, durations and dates | CPM schedule |
| Cost | Time-phased budget by WBS element, including contingency | Estimate plus the schedule |
These have to agree. A cost baseline built on a different scope breakdown from the schedule can't be used for earned value.
What goes into the cost baseline
The cost baseline is the approved budget spread over time. It includes the cost of the work packages and the contingency for identified uncertainty. PMI's convention is that management reserve sits outside the baseline, in the overall project budget but not inside the baseline itself. Plotted cumulatively over time, the baseline gives the planned-spend S-curve.
The performance measurement baseline
When scope, schedule and cost baselines are integrated, they form the performance measurement baseline. It's the reference line for earned value management: planned value comes from it, and so do the budgets against which earned value is claimed.
Changing the baseline
Approved changes update the baseline. Variance, however, never does: if the project is over budget because of poor productivity, you don't move the baseline to hide it. Use these rules of thumb:
- Update the baseline for approved scope changes processed through change control (see change orders).
- Draw on contingency through a recorded transfer, not informally.
- Re-baseline completely only when the existing baseline is no longer a credible measure, for example after a major scope change or owner-directed reset, and keep the history of what it was.
Common mistakes
- Re-baselining to erase a bad variance.
- Baselining before the scope is stable enough, then changing it constantly.
- Cost and schedule baselines on different structures.
- No record of what changed and who approved it.
Baselines and the CCP
Baselines, variance and change control run through the CCP® syllabus, especially Domain 1 (Managing Project Costs). Our Domain 1 guide goes deeper, and CCP Complete Self-Paced Preparation covers the full exam.
Frequently asked questions
What is a project baseline?+
What is a cost baseline in project management?+
When should a project be re-baselined?+
What is the performance measurement baseline?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →