Why earned value beats a simple budget-vs-actual check
Suppose a project has spent exactly half its budget at the halfway point. On a budget-versus-actual report that looks perfect. But if only 40% of the work is finished, the project is in trouble, and the simple report hides it. Earned value fixes that by asking a third question: how much of the planned work have we actually completed, measured in budget terms?
That's the whole idea. Once you have the planned value of work, the earned value of work done and the actual cost, you can see cost and schedule performance separately and forecast where the project will finish.
The three numbers everything else comes from
| Term | Meaning | Plain question it answers |
|---|---|---|
| Planned Value (PV) | Budgeted cost of the work scheduled to date | How much work should we have done by now, in budget terms? |
| Earned Value (EV) | Budgeted cost of the work actually completed | How much work have we really done, in budget terms? |
| Actual Cost (AC) | What the completed work actually cost | What did we spend to get it done? |
| Budget at Completion (BAC) | Total approved budget for the work | What was the whole job supposed to cost? |
The core formulas
| Measure | Formula | How to read it |
|---|---|---|
| Cost variance (CV) | EV − AC | Negative = over budget |
| Schedule variance (SV) | EV − PV | Negative = behind schedule (in budget terms) |
| Cost Performance Index (CPI) | EV ÷ AC | Below 1.0 = getting less than a dollar of work per dollar spent |
| Schedule Performance Index (SPI) | EV ÷ PV | Below 1.0 = progressing slower than planned |
| Estimate at Completion (EAC) | BAC ÷ CPI (one common method) | Forecast final cost if current cost efficiency continues |
| Estimate to Complete (ETC) | EAC − AC | How much more you expect to spend |
| Variance at Completion (VAC) | BAC − EAC | Negative = forecast overrun |
| To-Complete Performance Index (TCPI) | (BAC − EV) ÷ (BAC − AC) | The cost efficiency you'd need from now on to finish on budget |
There's more than one way to calculate EAC. BAC ÷ CPI assumes the cost performance so far will continue. Other methods assume future work will go to budget, or bring in schedule performance as well. Which one fits depends on why the project is off track, and that judgement is part of the job. Once a revised EAC is approved, TCPI is often calculated against it instead: (BAC − EV) ÷ (EAC − AC).
A worked example
A project has a budget at completion of $1,000,000. At the end of month 6, the schedule says $500,000 of work should be done (PV). Progress measurement shows $450,000 of budgeted work is actually complete (EV). Invoices and timesheets show $480,000 spent (AC).
| Measure | Calculation | Result |
|---|---|---|
| CV | 450,000 − 480,000 | −$30,000 (over budget) |
| SV | 450,000 − 500,000 | −$50,000 (behind schedule) |
| CPI | 450,000 ÷ 480,000 | 0.94 (about 94 cents of work per dollar) |
| SPI | 450,000 ÷ 500,000 | 0.90 |
| EAC | 1,000,000 ÷ 0.9375 | ≈ $1,066,667 |
| ETC | 1,066,667 − 480,000 | ≈ $586,667 |
| VAC | 1,000,000 − 1,066,667 | ≈ −$66,667 |
| TCPI | (1,000,000 − 450,000) ÷ (1,000,000 − 480,000) | ≈ 1.06 |
In words: the project is behind schedule and over budget. If cost performance stays where it is, it will finish about $66,700 over. To still finish on the original budget, every remaining dollar would have to deliver about $1.06 of work, which is a big ask for a project that's currently at 0.94. That's usually the signal to look at recovery options or a revised forecast rather than hoping performance turns around on its own.
Where earned value goes wrong in practice
The formulas are easy. The hard part is getting honest inputs. EV is only as good as your progress measurement; if percent-complete figures are optimistic, every index looks better than reality. Actual cost needs to include work done but not yet invoiced (accruals), or AC will look artificially low. And the baseline has to include approved changes, otherwise you're measuring against a plan that no longer exists.
It's also worth remembering that SPI is measured in money, not time. Near the end of a project it drifts back towards 1.0 even if the job finishes late, because eventually all the planned value is earned. For real schedule analysis, check the schedule itself.
Earned value on the CCP exam
Earned value runs through the CCP®. Domain 4, Conduct Performance Measurement/Analysis, has 20 of the 119 multiple-choice questions, and AACE's May 2026 blueprint includes tasks such as analysing earned value, interpreting CPI and SPI, and evaluating alignment between earned value and physical progress. Forecasting EAC also appears in Domain 1, the largest domain. Our CCP formulas guide collects the formulas in one place, and the S-curve guide shows how PV, EV and AC look on a chart.
Frequently asked questions
What is the difference between PV and EV?+
What does a CPI of 0.9 mean?+
How do you calculate EAC?+
What is TCPI?+
Is earned value on the CCP exam?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →