Earned Value Management Explained: PV, EV, AC, CPI, SPI and EAC With a Worked Example

By 3FOLD Training's CCP curriculum team · reviewed against the CCP Candidate Handbook · Updated 23 November 2026 · 9 min read

Quick answer: Earned value management (EVM) compares three numbers: Planned Value (PV), the budgeted cost of work scheduled; Earned Value (EV), the budgeted cost of work actually done; and Actual Cost (AC), what that work really cost. From them you get cost variance (EV − AC), schedule variance (EV − PV), the Cost Performance Index (CPI = EV ÷ AC) and the Schedule Performance Index (SPI = EV ÷ PV). A CPI or SPI below 1.0 means you're over budget or behind schedule.
Free Course Info

Get CCP® Training Details

Syllabus · LMS · Pricing — no spam.

Phone *

Your details are kept private and never shared.

Why earned value beats a simple budget-vs-actual check

Suppose a project has spent exactly half its budget at the halfway point. On a budget-versus-actual report that looks perfect. But if only 40% of the work is finished, the project is in trouble, and the simple report hides it. Earned value fixes that by asking a third question: how much of the planned work have we actually completed, measured in budget terms?

That's the whole idea. Once you have the planned value of work, the earned value of work done and the actual cost, you can see cost and schedule performance separately and forecast where the project will finish.

The three numbers everything else comes from

TermMeaningPlain question it answers
Planned Value (PV)Budgeted cost of the work scheduled to dateHow much work should we have done by now, in budget terms?
Earned Value (EV)Budgeted cost of the work actually completedHow much work have we really done, in budget terms?
Actual Cost (AC)What the completed work actually costWhat did we spend to get it done?
Budget at Completion (BAC)Total approved budget for the workWhat was the whole job supposed to cost?

The core formulas

MeasureFormulaHow to read it
Cost variance (CV)EV − ACNegative = over budget
Schedule variance (SV)EV − PVNegative = behind schedule (in budget terms)
Cost Performance Index (CPI)EV ÷ ACBelow 1.0 = getting less than a dollar of work per dollar spent
Schedule Performance Index (SPI)EV ÷ PVBelow 1.0 = progressing slower than planned
Estimate at Completion (EAC)BAC ÷ CPI (one common method)Forecast final cost if current cost efficiency continues
Estimate to Complete (ETC)EAC − ACHow much more you expect to spend
Variance at Completion (VAC)BAC − EACNegative = forecast overrun
To-Complete Performance Index (TCPI)(BAC − EV) ÷ (BAC − AC)The cost efficiency you'd need from now on to finish on budget

There's more than one way to calculate EAC. BAC ÷ CPI assumes the cost performance so far will continue. Other methods assume future work will go to budget, or bring in schedule performance as well. Which one fits depends on why the project is off track, and that judgement is part of the job. Once a revised EAC is approved, TCPI is often calculated against it instead: (BAC − EV) ÷ (EAC − AC).

A worked example

A project has a budget at completion of $1,000,000. At the end of month 6, the schedule says $500,000 of work should be done (PV). Progress measurement shows $450,000 of budgeted work is actually complete (EV). Invoices and timesheets show $480,000 spent (AC).

MeasureCalculationResult
CV450,000 − 480,000−$30,000 (over budget)
SV450,000 − 500,000−$50,000 (behind schedule)
CPI450,000 ÷ 480,0000.94 (about 94 cents of work per dollar)
SPI450,000 ÷ 500,0000.90
EAC1,000,000 ÷ 0.9375≈ $1,066,667
ETC1,066,667 − 480,000≈ $586,667
VAC1,000,000 − 1,066,667≈ −$66,667
TCPI(1,000,000 − 450,000) ÷ (1,000,000 − 480,000)≈ 1.06

In words: the project is behind schedule and over budget. If cost performance stays where it is, it will finish about $66,700 over. To still finish on the original budget, every remaining dollar would have to deliver about $1.06 of work, which is a big ask for a project that's currently at 0.94. That's usually the signal to look at recovery options or a revised forecast rather than hoping performance turns around on its own.

Where earned value goes wrong in practice

The formulas are easy. The hard part is getting honest inputs. EV is only as good as your progress measurement; if percent-complete figures are optimistic, every index looks better than reality. Actual cost needs to include work done but not yet invoiced (accruals), or AC will look artificially low. And the baseline has to include approved changes, otherwise you're measuring against a plan that no longer exists.

It's also worth remembering that SPI is measured in money, not time. Near the end of a project it drifts back towards 1.0 even if the job finishes late, because eventually all the planned value is earned. For real schedule analysis, check the schedule itself.

Earned value on the CCP exam

Earned value runs through the CCP®. Domain 4, Conduct Performance Measurement/Analysis, has 20 of the 119 multiple-choice questions, and AACE's May 2026 blueprint includes tasks such as analysing earned value, interpreting CPI and SPI, and evaluating alignment between earned value and physical progress. Forecasting EAC also appears in Domain 1, the largest domain. Our CCP formulas guide collects the formulas in one place, and the S-curve guide shows how PV, EV and AC look on a chart.

Frequently asked questions

What is the difference between PV and EV?+
PV is the budgeted cost of work you planned to have done by now. EV is the budgeted cost of the work you've actually done.
What does a CPI of 0.9 mean?+
A cost performance index (CPI) of 0.9 means you are getting 90 cents of planned work for every dollar spent, so the work is costing more than budgeted.
How do you calculate EAC?+
A common method is BAC ÷ CPI, which assumes current cost efficiency continues. Other methods exist for different situations.
What is TCPI?+
The cost efficiency needed on the remaining work to hit a target: (BAC − EV) ÷ (BAC − AC) for the original budget, or (BAC − EV) ÷ (EAC − AC) for a revised forecast.
Is earned value on the CCP exam?+
Yes, earned value management is on the CCP exam: performance measurement is Domain 4 (20 questions), and EAC forecasting also appears in Domain 1.

Prepare with an AACE-Approved Provider

2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.

Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →

WhatsAppEnrol — $590