PERT, the Program Evaluation and Review Technique, was developed for the US Navy's Polaris missile programme in the late 1950s, at about the same time as the critical path method. It was built to handle schedule uncertainty by giving each activity a range of durations rather than a single figure. The same three-point idea is now used for cost as well.
The formulas
- Expected value: E = (O + 4M + P) / 6. The most likely value gets four times the weight of the extremes.
- Standard deviation: σ ≈ (P − O) / 6. The range from best to worst case is treated as about six standard deviations.
- Variance: σ².
The simple average (O + M + P) / 3 is also used, particularly for a triangular distribution. PERT's weighting assumes a beta-type distribution that clusters around the most likely value.
A worked example
Three activities in sequence have these duration estimates in days:
| Activity | O | M | P | Expected | Std dev |
|---|---|---|---|---|---|
| A | 10 | 14 | 24 | 15.0 | 2.33 |
| B | 6 | 9 | 18 | 10.0 | 2.00 |
| C | 8 | 10 | 14 | 10.3 | 1.00 |
| Total | 35.3 | 3.23 |
Expected durations simply add: 15.0 + 10.0 + 10.3 = 35.3 days. For standard deviation you add the variances (2.33² + 2.00² + 1.00² = 5.44 + 4.00 + 1.00 = 10.44) and take the square root: σ ≈ 3.23 days, assuming the activities are independent.
Under a normal approximation, there's about a 68% chance of finishing within one standard deviation of the expected value, so roughly 32 to 39 days. The chance of finishing in the expected time itself is only about 50%. That's why a schedule built on expected durations is often later than planned.
Limits
- Optimism bias. People tend to give ranges that are too narrow, so the estimate looks more certain than it is.
- Independence. Adding variances assumes the activities don't affect each other. In practice the same weather, supplier or crew can affect several activities at once, which widens the real spread.
- Parallel paths. On a network, near-critical paths can also finish late, so the project is usually later than the single critical path's expected value suggests.
For cost, the same idea scales up into simulation: see Monte Carlo cost risk analysis. For single risk events with a probability, use expected monetary value instead.
PERT and the CCP
Scheduling and risk analysis are CCP® exam topics, and estimating with ranges underpins contingency. CCP Complete Self-Paced Preparation covers these areas.
Frequently asked questions
What is the PERT formula?+
How do you calculate standard deviation in PERT?+
What is the difference between PERT and three-point estimating?+
Do you add standard deviations for a chain of activities?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →