Get CCP® Training Details
Syllabus · LMS · Pricing — no spam.
Why single-point estimates aren't enough
Every line in an estimate is really a range, not one number. If each line is its most likely value, the total is the sum of most-likely values, which is not the most likely total, and it's rarely the number you'll actually spend. Monte Carlo simulation is a way to combine many uncertain lines into a realistic picture of total cost.
How it works
- Give each cost item (or risk) a range: usually a low, most likely and high value, forming a three-point distribution.
- Set correlations where items move together, for instance, if steel prices rise, several steel-related items rise.
- Run the model many times (PMI's paper on the method suggests about 1,000 iterations; modern software commonly runs thousands). Each run picks a random value for each item from its range and adds them up.
- Plot the results as a distribution of total cost, and read off percentile values.
A worked example
Five work packages for a small project, in thousands of dollars, each with a triangular distribution (low / most likely / high):
| Item | Low | Most likely | High |
|---|---|---|---|
| Earthworks | 380 | 420 | 520 |
| Structure | 900 | 1,000 | 1,250 |
| MEP | 600 | 680 | 900 |
| Finishes | 300 | 330 | 420 |
| Externals | 150 | 170 | 240 |
| Sum of values | 2,330 | 2,600 | 3,330 |
The sum of most-likely values is 2,600. I ran 10,000 trials of this model, treating the items as independent. The results were roughly: P10 ≈ 2,620, P50 ≈ 2,750, P80 ≈ 2,850 and P90 ≈ 2,890. These numbers come from my own illustrative run, not a real project.
Two points stand out. First, even the 'most likely' plan of 2,600 sits below the P10, so it's very unlikely to be enough; because each item's high side is farther from its most likely value than its low side, the total drifts upward. Second, the difference between the P80 and the 2,600 sum is about 250, around 10% of the base. That's the contingency, if the sponsor chooses an 80% confidence level, for the uncertainty captured in these ranges.
P50, P80 and who decides
A P50 is the value with a 50% chance of not being exceeded; P80, 80%. There's no universal right level. The sponsor chooses a confidence level based on its appetite for risk and the consequences of an overrun. In the PMI paper's worked example, the probability level was set by the sponsor, and contingency was the difference between the simulated value at that level and the base estimate.
Correlation: the part people skip
I treated my items as independent. In real projects they aren't: the same market conditions, productivity or management quality affect several items together. Ignoring that makes the simulated range too narrow, and the model more confident than reality justifies. That's why AACE's recommended practice on estimate ranging gives specific attention to correlation, and why it's considered one of the hardest parts of doing this well.
Limits of the method
- Garbage in, garbage out. Ranges based on gut feel produce precise-looking nonsense.
- Ranging only captures inherent uncertainty. AACE's RP 118R-21, which covers estimate ranging with Monte Carlo simulation for inherent risks, says it suits well-defined scope (Class 3 or better) with minimal complexity, and notes that ranging tends to underestimate contingency when project-specific risks are significant.
- Specific risks need their own treatment. AACE's RP 44R-08 covers risk analysis and contingency determination using expected value (probability times impact) for project-specific risks.
AACE guidance
AACE International publishes recommended practices for these methods, including RP 41R-08 (on understanding estimate ranging), RP 44R-08 (expected value) and RP 118R-21. They're available to members, and non-members can purchase them. For the underlying concept of contingency, see contingency vs management reserve.
Risk analysis and the CCP
Risk management and contingency are part of the CCP® exam, and expected monetary value is one of its calculation topics (see our formula guide). CCP Complete Self-Paced Preparation covers the exam domains.
Frequently asked questions
What is Monte Carlo simulation in cost estimating?+
What do P50 and P80 mean in cost risk analysis?+
Why does correlation matter in Monte Carlo cost simulation?+
Is Monte Carlo simulation the same as expected value analysis for project risk?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →
