The formula
EMV = probability × impact. A risk with a 30% chance of costing 200,000 has an EMV of 60,000. Opportunities are positive impacts, and threats are negative. The sum of EMVs across independent risks is the expected total.
A worked risk register
| Risk | Probability | Impact | EMV |
|---|---|---|---|
| Late steel delivery | 30% | 200,000 | 60,000 |
| Ground conditions worse than surveyed | 20% | 350,000 | 70,000 |
| Authority approval delay | 10% | 500,000 | 50,000 |
| Design change by client | 40% | 60,000 | 24,000 |
| Total | 204,000 |
The expected cost of these four risks is 204,000. Notice that no single outcome costs 204,000. If none happen, the cost is zero; if all happen, it is 1,110,000. The expected value is an average across possibilities.
Using EMV for contingency
AACE's recommended practice 44R-08, Risk Analysis and Contingency Determination Using Expected Value, covers using probability times impact for quantitative risk analysis of project-specific risks and says best practice calls for probabilistic methods that produce a cost distribution, applied through Monte Carlo simulation, rather than relying on the mean alone. If only the mean is needed, no further analysis is required. The expected value gives a central figure, and a simulation shows how likely different totals are (see Monte Carlo cost risk analysis and contingency vs management reserve).
Decision trees
EMV is also used to compare decisions with uncertain outcomes. Example: pay 40,000 for extra ground investigation that has a 25% chance of revealing a problem that would otherwise cost 300,000 more to fix later. If the investigation avoids that cost when it finds the problem, the expected saving is 0.25 × 300,000 = 75,000, which exceeds the 40,000 cost, so the investigation has a positive expected value of 35,000. This ignores other benefits and the time value of money, so treat it as a guide to the decision, not the answer.
Limits
- Averages hide the spread. A 1% chance of a 10 million loss has an EMV of 100,000 but a very different consequence from a certain 100,000 cost.
- Probability estimates are judgements. Give them a basis, and don't give false precision.
- Independence. Summing EMVs ignores links between risks, for example weather delaying several activities at once.
- Inherent uncertainty. EMV handles discrete events. Estimate uncertainty, such as rate variation, needs range methods (see three-point estimating).
EMV and the CCP
Expected monetary value is one of the calculation topics in the CCP® exam's risk domain; our formula guide lists it with the other formulas. CCP Complete Self-Paced Preparation covers the risk domain alongside the others.
Frequently asked questions
What is expected monetary value (EMV)?+
How do you calculate EMV for multiple risks?+
Is EMV the same as contingency?+
What are the limitations of expected monetary value?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →