New Study Guide for the 2026 CCP® Exam Blueprint
3FOLD Training — AACE-Approved CCP Exam Prep
Industry Guide

Expected Monetary Value (EMV): Formula, Example and Using It for Contingency

By 3FOLD Training's CCP curriculum team · reviewed against the CCP Candidate Handbook · Updated 24 November 2026 · 6 min read

Quick answer: Expected monetary value (EMV) is the probability of a risk event multiplied by its cost impact. Summing the EMV of all identified risks gives an expected cost of risk, which can inform contingency. It's simple and widely used for project-specific risks, but an average hides the spread, so it works best alongside ranges or simulation.
Free Course Info

Get CCP® Training Details

Syllabus · LMS · Pricing — no spam.

Phone *

Your details are kept private and never shared.

The formula

EMV = probability × impact. A risk with a 30% chance of costing 200,000 has an EMV of 60,000. Opportunities are positive impacts, and threats are negative. The sum of EMVs across independent risks is the expected total.

A worked risk register

RiskProbabilityImpactEMV
Late steel delivery30%200,00060,000
Ground conditions worse than surveyed20%350,00070,000
Authority approval delay10%500,00050,000
Design change by client40%60,00024,000
Total204,000

The expected cost of these four risks is 204,000. Notice that no single outcome costs 204,000. If none happen, the cost is zero; if all happen, it is 1,110,000. The expected value is an average across possibilities.

Using EMV for contingency

AACE's recommended practice 44R-08, Risk Analysis and Contingency Determination Using Expected Value, covers using probability times impact for quantitative risk analysis of project-specific risks and says best practice calls for probabilistic methods that produce a cost distribution, applied through Monte Carlo simulation, rather than relying on the mean alone. If only the mean is needed, no further analysis is required. The expected value gives a central figure, and a simulation shows how likely different totals are (see Monte Carlo cost risk analysis and contingency vs management reserve).

Decision trees

EMV is also used to compare decisions with uncertain outcomes. Example: pay 40,000 for extra ground investigation that has a 25% chance of revealing a problem that would otherwise cost 300,000 more to fix later. If the investigation avoids that cost when it finds the problem, the expected saving is 0.25 × 300,000 = 75,000, which exceeds the 40,000 cost, so the investigation has a positive expected value of 35,000. This ignores other benefits and the time value of money, so treat it as a guide to the decision, not the answer.

Limits

  • Averages hide the spread. A 1% chance of a 10 million loss has an EMV of 100,000 but a very different consequence from a certain 100,000 cost.
  • Probability estimates are judgements. Give them a basis, and don't give false precision.
  • Independence. Summing EMVs ignores links between risks, for example weather delaying several activities at once.
  • Inherent uncertainty. EMV handles discrete events. Estimate uncertainty, such as rate variation, needs range methods (see three-point estimating).

EMV and the CCP

Expected monetary value is one of the calculation topics in the CCP® exam's risk domain; our formula guide lists it with the other formulas. CCP Complete Self-Paced Preparation covers the risk domain alongside the others.

Frequently asked questions

What is expected monetary value (EMV)?+
Expected monetary value (EMV) is the probability of a risk event multiplied by its cost impact, so a 30% chance of a 200,000 loss has an EMV of 60,000.
How do you calculate EMV for multiple risks?+
To calculate EMV for multiple risks, multiply each risk's probability by its impact and add the results, which gives the expected total cost of the risks, assuming they are independent.
Is EMV the same as contingency?+
No, expected monetary value is an input to contingency, not the same thing; AACE guidance notes that best practice uses probabilistic methods such as Monte Carlo simulation to produce a cost distribution rather than relying on the mean alone.
What are the limitations of expected monetary value?+
Expected monetary value hides the spread of outcomes, depends on subjective probability estimates and assumes risks are independent, so it is best used with ranges or simulation.

Prepare with an AACE-Approved Provider

2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.

Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →

WhatsAppEnrol — $590