The terms you need
EAC builds on the earned value measures. BAC is the budget at completion, EV the earned value, AC the actual cost, CPI = EV / AC and SPI = EV / PV (planned value). All forecasts below answer the same question: what will the project cost in total?
The four EAC formulas
| Formula | Assumption behind it |
|---|---|
| EAC = BAC / CPI | Cost performance to date will continue for the rest of the work |
| EAC = AC + (BAC − EV) | The overrun so far was a one-off; the remaining work will cost what was budgeted |
| EAC = AC + (BAC − EV) / (CPI × SPI) | Both cost and schedule performance affect the remaining cost, for example when delay forces extra resources |
| EAC = AC + new bottom-up ETC | The original plan is no longer valid, so the remaining work is re-estimated |
ETC (estimate to complete) is the cost still to be spent, so EAC = AC + ETC. VAC (variance at completion) is BAC − EAC: negative means a forecast overrun.
A worked example
A project has BAC = 2,000,000. To date: PV = 850,000, EV = 800,000, AC = 900,000.
- CPI = 800,000 / 900,000 = 0.889. SPI = 800,000 / 850,000 = 0.941.
- EAC = BAC / CPI = 2,000,000 / 0.889 = 2,250,000. VAC = −250,000.
- EAC = AC + (BAC − EV) = 900,000 + 1,200,000 = 2,100,000.
- EAC = AC + (BAC − EV) / (CPI × SPI) = 900,000 + 1,200,000 / 0.837 ≈ 2,334,000.
Three formulas, three answers, from 2.10 million to 2.33 million. That spread is useful information. It tells the project manager the forecast depends on whether the early overrun was a one-off or a trend.
TCPI: what performance do we need from here?
The to-complete performance index shows the cost efficiency required on remaining work to hit a target. To hit the original budget: TCPI = (BAC − EV) / (BAC − AC) = 1,200,000 / 1,100,000 = 1.09. The project has been running at 0.89 and now needs 1.09 for the rest. That's a large swing, and a good reason to doubt the original budget is still achievable. PMI's paper on TCPI sets out the same formula, and the TCPI to hit a revised EAC is calculated by replacing BAC with that target in the numerator and AC in the denominator.
Which formula should I use?
- Cause was a one-off (a single rework event, a price spike that has passed): the AC + (BAC − EV) formula is defensible.
- Performance is a trend (productivity, estimate quality): BAC / CPI is the normal starting point.
- Schedule pressure is driving cost: the CPI × SPI version is more cautious.
- The plan has changed: re-estimate the remaining work bottom-up and add it to AC.
Whichever you choose, state the assumption in the report. A forecast with no stated basis is hard to challenge and hard to trust. See cost control in construction for how forecasting fits into monthly reporting.
EAC on the CCP exam
Forecasting with EAC appears in the CCP® exam, which provides an on-screen formula sheet, but you still need to know which formula applies to which scenario. Our CCP formula guide covers the full set, and CCP Complete Self-Paced Preparation includes a formula sheet and three mock exams.
Frequently asked questions
What is estimate at completion (EAC)?+
What is the most common EAC formula?+
What is the difference between EAC and ETC?+
What does a TCPI above 1.0 mean?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →