Estimate at Completion (EAC): The Four Formulas and When to Use Each

By 3FOLD Training's CCP curriculum team · reviewed against the CCP Candidate Handbook · Updated 24 November 2026 · 7 min read

Quick answer: Estimate at completion (EAC) is a forecast of the total cost of a project when it finishes. The most-used formulas are EAC = BAC / CPI (current cost performance continues), EAC = AC + (BAC − EV) (the remaining work will be done at budget), EAC = AC + (BAC − EV) / (CPI × SPI) (cost and schedule performance both affect the remainder) and EAC = AC + a new bottom-up estimate to complete. Which one to use depends on why the project is off plan.
Free Course Info

Get CCP® Training Details

Syllabus · LMS · Pricing — no spam.

Phone *

Your details are kept private and never shared.

The terms you need

EAC builds on the earned value measures. BAC is the budget at completion, EV the earned value, AC the actual cost, CPI = EV / AC and SPI = EV / PV (planned value). All forecasts below answer the same question: what will the project cost in total?

The four EAC formulas

FormulaAssumption behind it
EAC = BAC / CPICost performance to date will continue for the rest of the work
EAC = AC + (BAC − EV)The overrun so far was a one-off; the remaining work will cost what was budgeted
EAC = AC + (BAC − EV) / (CPI × SPI)Both cost and schedule performance affect the remaining cost, for example when delay forces extra resources
EAC = AC + new bottom-up ETCThe original plan is no longer valid, so the remaining work is re-estimated

ETC (estimate to complete) is the cost still to be spent, so EAC = AC + ETC. VAC (variance at completion) is BAC − EAC: negative means a forecast overrun.

A worked example

A project has BAC = 2,000,000. To date: PV = 850,000, EV = 800,000, AC = 900,000.

  • CPI = 800,000 / 900,000 = 0.889. SPI = 800,000 / 850,000 = 0.941.
  • EAC = BAC / CPI = 2,000,000 / 0.889 = 2,250,000. VAC = −250,000.
  • EAC = AC + (BAC − EV) = 900,000 + 1,200,000 = 2,100,000.
  • EAC = AC + (BAC − EV) / (CPI × SPI) = 900,000 + 1,200,000 / 0.837 ≈ 2,334,000.

Three formulas, three answers, from 2.10 million to 2.33 million. That spread is useful information. It tells the project manager the forecast depends on whether the early overrun was a one-off or a trend.

TCPI: what performance do we need from here?

The to-complete performance index shows the cost efficiency required on remaining work to hit a target. To hit the original budget: TCPI = (BAC − EV) / (BAC − AC) = 1,200,000 / 1,100,000 = 1.09. The project has been running at 0.89 and now needs 1.09 for the rest. That's a large swing, and a good reason to doubt the original budget is still achievable. PMI's paper on TCPI sets out the same formula, and the TCPI to hit a revised EAC is calculated by replacing BAC with that target in the numerator and AC in the denominator.

Which formula should I use?

  • Cause was a one-off (a single rework event, a price spike that has passed): the AC + (BAC − EV) formula is defensible.
  • Performance is a trend (productivity, estimate quality): BAC / CPI is the normal starting point.
  • Schedule pressure is driving cost: the CPI × SPI version is more cautious.
  • The plan has changed: re-estimate the remaining work bottom-up and add it to AC.

Whichever you choose, state the assumption in the report. A forecast with no stated basis is hard to challenge and hard to trust. See cost control in construction for how forecasting fits into monthly reporting.

EAC on the CCP exam

Forecasting with EAC appears in the CCP® exam, which provides an on-screen formula sheet, but you still need to know which formula applies to which scenario. Our CCP formula guide covers the full set, and CCP Complete Self-Paced Preparation includes a formula sheet and three mock exams.

Frequently asked questions

What is estimate at completion (EAC)?+
Estimate at completion (EAC) is a forecast of the total cost of a project when it is finished, equal to actual cost to date plus the estimate to complete (EAC = AC + ETC).
What is the most common EAC formula?+
The most common estimate at completion formula is EAC = BAC / CPI, which assumes the cost performance achieved so far continues for the rest of the project.
What is the difference between EAC and ETC?+
Estimate at completion (EAC) is the forecast total project cost, while estimate to complete (ETC) is only the cost still to be spent; EAC equals actual cost plus ETC.
What does a TCPI above 1.0 mean?+
A to-complete performance index (TCPI) above 1.0 means the project must achieve better cost efficiency than it has so far to finish within the target, which becomes harder as TCPI rises.

Prepare with an AACE-Approved Provider

2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.

Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →

WhatsAppEnrol — $590