Fixed-Price vs Cost-Plus Contracts: How Each Allocates Cost Risk

By 3FOLD Training's CCP curriculum team · reviewed against the CCP Candidate Handbook · Updated 24 November 2026 · 7 min read

Quick answer: In a fixed-price (lump-sum) contract the contractor agrees to deliver defined scope for a set price, so the contractor carries most cost risk. In a cost-plus (cost-reimbursable) contract the owner pays the actual allowable cost plus a fee, so the owner carries most cost risk. Target-cost and unit-price contracts share risk between the two. The right choice depends on how well the scope is defined.
Free Course Info

Get CCP® Training Details

Syllabus · LMS · Pricing — no spam.

Phone *

Your details are kept private and never shared.

A contract is a way of allocating risk

The contract type decides who pays when costs turn out different from the estimate. That makes it a cost-control decision as much as a legal one. It affects how you budget, how you hold contingency, and how much effort goes into tracking cost.

The main types

Fixed-price (lump sum)

The contractor agrees to complete a defined scope for a fixed sum. It gives the owner cost certainty, if the scope is complete and stable. The price usually includes the contractor's pricing of risk, and changes are paid as variations (see change orders and variations). It suits well-defined work.

Unit-price (measure and value)

The contractor prices each unit of work, often from a bill of quantities, and is paid for quantities actually measured. Quantity risk stays with the owner, price risk with the contractor. It's common where quantities are uncertain, such as earthworks.

Cost-reimbursable (cost-plus)

The owner pays the contractor's actual allowable costs plus a fee, which may be a fixed amount, a percentage or tied to performance. It suits work whose scope isn't defined enough to price. Because the owner carries the risk, it needs strong cost control and audit rights. A fee set as a percentage of cost is widely criticised because it rewards higher spending.

Target-cost (incentive)

Costs are reimbursed against an agreed target, and an agreed share of any saving or overrun goes to each party (a pain/gain share). It aligns incentives, but depends on a credible target and good cost data.

Time and materials

The contractor is paid for hours and materials at agreed rates, often with a ceiling. It suits small or urgent work.

Who carries the risk

Contract typeCost risk mostly withBest when
Fixed-priceContractorScope is complete and stable
Unit-priceShared (quantity: owner; rate: contractor)Scope known, quantities uncertain
Target-costShared by agreed formulaCollaboration and incentives are wanted
Cost-reimbursableOwnerScope undefined or evolving
Time and materialsOwner (capped if ceiling set)Small, urgent or unclear work

Standard forms use these ideas under different names. For example, NEC's Engineering and Construction Contract offers main options that range from priced contracts to target-cost and cost-reimbursable. Always read the clauses for your actual contract.

What it means for cost control

  • Under fixed-price, the owner's focus is change control and valuing variations, because overrun risk has moved to the contractor.
  • Under cost-reimbursable or target-cost, the owner needs detailed cost reporting, audit of invoices and early forecasts. See cost control in construction.
  • Whatever the type, a contractor in financial difficulty is an owner risk. Watch cash flow and progress, not just the price.

Contracts and the CCP

Contracts and procurement are part of the cost engineer's working knowledge, and the CCP® covers how project functions interface with cost management. See CCP Complete Self-Paced Preparation for coverage of the exam domains. This article is general information, not legal advice.

Frequently asked questions

What is the difference between a fixed-price and a cost-plus contract?+
In a fixed-price contract the contractor agrees to deliver defined scope for a set sum and carries most cost risk, while in a cost-plus contract the owner pays actual allowable costs plus a fee and carries most cost risk.
When should I use a cost-reimbursable contract?+
A cost-reimbursable contract suits work whose scope is not defined well enough to price, such as early-stage or evolving projects, but it needs strong cost control and audit rights because the owner carries the risk.
What is a target-cost contract?+
A target-cost contract reimburses costs against an agreed target and shares any saving or overrun between owner and contractor by an agreed formula, which aligns the parties' incentives.
What is a unit-price contract?+
A unit-price contract pays the contractor an agreed rate for each unit of work actually measured, so the owner carries quantity risk and the contractor carries the risk of its rates.

Prepare with an AACE-Approved Provider

2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.

Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →

WhatsAppEnrol — $590