A contract is a way of allocating risk
The contract type decides who pays when costs turn out different from the estimate. That makes it a cost-control decision as much as a legal one. It affects how you budget, how you hold contingency, and how much effort goes into tracking cost.
The main types
Fixed-price (lump sum)
The contractor agrees to complete a defined scope for a fixed sum. It gives the owner cost certainty, if the scope is complete and stable. The price usually includes the contractor's pricing of risk, and changes are paid as variations (see change orders and variations). It suits well-defined work.
Unit-price (measure and value)
The contractor prices each unit of work, often from a bill of quantities, and is paid for quantities actually measured. Quantity risk stays with the owner, price risk with the contractor. It's common where quantities are uncertain, such as earthworks.
Cost-reimbursable (cost-plus)
The owner pays the contractor's actual allowable costs plus a fee, which may be a fixed amount, a percentage or tied to performance. It suits work whose scope isn't defined enough to price. Because the owner carries the risk, it needs strong cost control and audit rights. A fee set as a percentage of cost is widely criticised because it rewards higher spending.
Target-cost (incentive)
Costs are reimbursed against an agreed target, and an agreed share of any saving or overrun goes to each party (a pain/gain share). It aligns incentives, but depends on a credible target and good cost data.
Time and materials
The contractor is paid for hours and materials at agreed rates, often with a ceiling. It suits small or urgent work.
Who carries the risk
| Contract type | Cost risk mostly with | Best when |
|---|---|---|
| Fixed-price | Contractor | Scope is complete and stable |
| Unit-price | Shared (quantity: owner; rate: contractor) | Scope known, quantities uncertain |
| Target-cost | Shared by agreed formula | Collaboration and incentives are wanted |
| Cost-reimbursable | Owner | Scope undefined or evolving |
| Time and materials | Owner (capped if ceiling set) | Small, urgent or unclear work |
Standard forms use these ideas under different names. For example, NEC's Engineering and Construction Contract offers main options that range from priced contracts to target-cost and cost-reimbursable. Always read the clauses for your actual contract.
What it means for cost control
- Under fixed-price, the owner's focus is change control and valuing variations, because overrun risk has moved to the contractor.
- Under cost-reimbursable or target-cost, the owner needs detailed cost reporting, audit of invoices and early forecasts. See cost control in construction.
- Whatever the type, a contractor in financial difficulty is an owner risk. Watch cash flow and progress, not just the price.
Contracts and the CCP
Contracts and procurement are part of the cost engineer's working knowledge, and the CCP® covers how project functions interface with cost management. See CCP Complete Self-Paced Preparation for coverage of the exam domains. This article is general information, not legal advice.
Frequently asked questions
What is the difference between a fixed-price and a cost-plus contract?+
When should I use a cost-reimbursable contract?+
What is a target-cost contract?+
What is a unit-price contract?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →