What a bill of quantities is
A BOQ turns the drawings and specification into a structured list of what has to be built, with a quantity for each item: so many cubic metres of concrete, so many square metres of blockwork, so many metres of pipe. The quantities may be measured by number, length, area, volume, weight or time. It is prepared by the client's cost consultant, usually a quantity surveyor (see cost engineer vs quantity surveyor), so every tenderer prices exactly the same scope.
What's in a BOQ
- Preliminaries: the contractor's general costs and obligations, such as site set-up, management, temporary works and insurances, rather than permanent work.
- Measured work: the permanent works, grouped into work sections such as concrete, masonry or mechanical services, with a description, unit and quantity for each item.
- Provisional sums: allowances for work not yet defined enough to measure.
- Summary and collection pages that bring the sections to one total.
Unpriced and priced
The client issues an unpriced bill (sometimes called the tender pricing document) to tenderers. Each adds rates and totals, producing a priced bill that is their complete offer. After award, the priced bill carries real contractual weight: it supports the contract sum, interim payments, the valuation of variations and the final account.
Measurement rules: NRM2 and SMM7
Everyone has to measure the same way, otherwise two bills aren't comparable. In the UK, the Standard Method of Measurement (SMM7) was replaced by RICS's New Rules of Measurement 2 (NRM2), published in April 2012 and operative from January 2013, which sets detailed measurement rules for building works. NRM2 is one of three volumes: NRM1 covers cost estimating and cost planning, and NRM3 covers cost planning for maintenance works. Other countries and sectors use their own methods; civil engineering work in several regions, for example, has its own measurement standards. Always confirm which method the contract names.
How a priced BOQ is used on site
- Interim valuations: measure work done and apply the rates for each item to value monthly payments.
- Variations: where changed work resembles a billed item, the bill rate often provides the pricing basis (see change orders and variations).
- Cost control: the bill gives a detailed baseline to compare against forecast cost (see cost control in construction).
Common mistakes
- Issuing the bill on incomplete drawings, leaving large provisional sums that later turn into variations.
- Ambiguous item descriptions that let each side read the scope differently.
- Ignoring front-loaded rates. Unbalanced pricing makes early valuations look better than real progress.
- Treating the BOQ as the whole contract. The conditions, drawings and specification matter just as much.
Where the CCP fits
The BOQ is a quantity surveying tool, and the CCP® is a broader cost engineering certification, but understanding how bills feed estimates and valuations helps in either role. See our cost engineering guide and CCP Complete Self-Paced Preparation.
Frequently asked questions
What is a bill of quantities (BOQ)?+
Who prepares a bill of quantities?+
What is NRM2 in a bill of quantities?+
What is the difference between a priced and an unpriced bill of quantities?+
Prepare with an AACE-Approved Provider
2026-blueprint study guide, video lessons, 3 full-length simulations, memo guidance — $590, 180 days.
Sources: AACE International CCP Candidate Handbook (rev. June 2026) and AACE's official CCP certification pages. CCP® is a registered mark of AACE International. More CCP articles →